2020
GEB and Trecsa v. Guatemala (I) Grupo Energía Bogotá S.A. E.S.P. and Transportadora de Energía de Centroamérica S.A. v. Republic of Guatemala (I) (ICSID Case No. ARB/20/48)
Guatemala
Colombia
Rights under a contract with the government for the construction, operation and maintenance of electricity transmission lines.
Claims arising out of the Government’s refusal to compensate the claimants for costs and delays that were allegedly caused by the Government related to the claimants’ execution of a construction contract for electricity transmission lines.
Tertiary: D - Electricity, gas, steam and air conditioning supply
Tertiary: F - Construction
35 - Electricity, gas, steam and air conditioning supply
42 - Civil engineering
ICSID (International Centre for Settlement of Investment Disputes)
ICSID (International Centre for Settlement of Investment Disputes)
Siqueiros, E.
Mourre, A.
Ramírez Hernández, R.
230.00 mln USD
Data not available
Indirect expropriation

Fair and equitable treatment/Minimum standard of treatment, including denial of justice claims

Full protection and security, or similar

Most-favoured nation treatment

Umbrella clause
Pending