2018
Manolium Processing v. Belarus OOO Manolium Processing v. The Republic of Belarus (PCA Case No. 2018-06)
Belarus
Russian Federation
Contract concluded with the Government for the construction of buildings in Minsk and its outskirts.
Claims arising out of the Government’s termination of a 2003 investment agreement to develop land in Minsk for the construction of a luxury hotel, upon vacating the area from a trolley bus parking facility and rebuilding it on the city outskirts. Challenged measures also include the alleged confiscation of the relocated facility by the Government in order to cover a USD 20 million tax debt imposed on the claimant.
Tertiary: F - Construction
41 - Construction of buildings
UNCITRAL
PCA (Permanent Court of Arbitration)
Fernández-Armesto, J.
Alexandrov, S. A.
Stern, B.
Data not available
Data not available
Data not available
Pending
None