2015
STEAG v. Spain STEAG GmbH v. Kingdom of Spain (ICSID Case No. ARB/15/4)
Spain
Germany
Shareholding in the Spanish thermosolar power plant Arenales.
Claims arising out of a series of energy reforms undertaken by the Government affecting the renewables sector.
Tertiary: D - Electricity, gas, steam and air conditioning supply
35 - Electricity, gas, steam and air conditioning supply
ICSID (International Centre for Settlement of Investment Disputes)
ICSID (International Centre for Settlement of Investment Disputes)
Tawil, G. S.
Dupuy, P.-M.
Zuleta, E.
Decided in favour of investor
79.00 mln EUR (92.90 mln USD)
27.70 mln EUR (32.60 mln USD)
Fair and equitable treatment/Minimum standard of treatment, including denial of justice claims

Full protection and security, or similar

Umbrella clause

Indirect expropriation
Fair and equitable treatment/Minimum standard of treatment, including denial of justice claims
ICSID annulment proceedings
ICSID annulment proceedings
Pending
None
Kalnina, E. (President)

Argueta Pinto, M. (Member)

Vásquez Urra, R. (Member)