2017
Agro EcoEnergy and others v. Tanzania Agro EcoEnergy Tanzania Limited, Bagamoyo EcoEnergy Limited, EcoDevelopment in Europe AB, EcoEnergy Africa AB v. United Republic of Tanzania (ICSID Case No. ARB/17/33)
Tanzania, United Republic of
Sweden
Investment of the alleged USD 52 million in developing 20,000 hectares of land to grow sugar cane and produce ethanol.
Claims arising out of the cancellation by the Government, in 2016, of the claimants’ sugar cane and ethanol project on the grounds that it would have adverse impact on local wildlife.
Primary: A - Agriculture, forestry and fishing
Secondary: C - Manufacturing
1 - Crop and animal production, hunting and related service activities
20 - Manufacture of chemicals and chemical products
ICSID (International Centre for Settlement of Investment Disputes)
ICSID (International Centre for Settlement of Investment Disputes)
Greenwood, C.
Alexandrov, S. A.
Adekoya, O.
Data not available
Data not available
Data not available
Data not available
Pending
None